Project Information
Project Information
#5 Mt. Hood to Chemult (MHC) - Bundle 101 Region 1 & 4
 
Location:  OR224, US26, and Clackamas, Mt. Hood, Warm Springs and The Dalles-CA Highways
Design-Builder:  Wildish Standard Paving Co.
Design Firm:  David Evans & Associates (DEA)
Award Date:  April 27, 2004
Contract Amount:  $30,537,040
Specified Contract Completion Date:  June 26, 2006
Actual Contract Completion Date:  June 22, 2006
 
The Mt. Hood to Chemult Design-Build project replaced eleven (11) bridges and removed one (1) bridge on Highways OR224, US26 and US97, together with roadwork to add northbound and southbound passing lanes between MP 199.8 and 201.2 on US97 near Chemult.  All of the bridges were replaced as part of the statewide OTIA III Bridge Program.
 
This was the second corridor level Design-Build project in Oregon.
 
Final Exemption Report (5-29-07)
 
 
For more information about this project contact:
Brenda Marcus, ODOT Design-Build Project Manager @ (503) 986-6638 or by Email at

 