| Stateline Wind Project |
|
|
 |
|
|
Facility: Wind energy facility
Current operating capacity: 123 MW (Stateline 1&2)
Approved but not built: 100 MW (Stateline 3)
Location: Umatilla County
Status:
The Council has approved Amendment #4, authorizing a third phase of construction (Stateline 3) consisting of up to 100.5 MW of additional generating capacity.
Certificate Holders : FPL Energy Vansycle LLC and FPL Energy Stateline II, Inc.
Contact:
William M. Hayduk
NextEra Energy Resources, Inc.
700 Universe Boulevard
P.O. Box 14000
Juno Beach, FL 33408-0420
(561) 304-5108
Department of Energy staff: John White
Original site certificate signed: September 14, 2001
Current site certificate: Fourth Amended Site Certificate (effective May 19, 2009)
History:
- April 27, 2000: Request for Expedited Review submitted.
- January 11, 2001: Application submitted.
- May 11, 2001: Application complete (date of filing).
- July 2, 2001: Department of Energy issued a draft proposed order.
- September 14, 2001: Council approved a site certificate.
- January 22, 2002: Request for Amendment #1 received.
- April 11, 2002: Department of Energy issued a proposed order on Amendment #1.
- May 17, 2002: Council approved Amendment #1.
- July 1, 2002: Request for Amendment #2 received.
- November 15, 2002: Revised request for Amendment #2 received.
- February 11, 2003: Request for Addendum received.
- March 25, 2003: Department of Energy issued a proposed order on Amendment #2.
- June 6, 2003: Council approved Amendment #2.
- March 25, 2005: Request for Amendment #3 received.
- May 19, 2005: Department of Energy issued a proposed order on Amendment #3.
- June 20, 2005: Council approved Amendment #3.
- January 20, 2006: Council approved revisions to the Oregon Wildlife Monitoring Plan.
- December 26, 2006: Request for Amendment #4 received (withdrawn).
- October 24, 2008: Revised Request for Amendment #4 received.
- February 20, 2009: Department of Energy issued a proposed order on Amendment #4.
- March 27, 2009: Council approved Amendment #4.
- May 19, 2009: Effective date of Fourth Amended Site Certificate.
Documents:
- Final Order, September 2001
Attachment A (wildlife monitoring) Attachment B (revegetation)
- Site Certificate, September 2001
- Final Order on Amendment #1, May 2002
Attachment A (wildlife montoring) Attachment B (revegetation)
- First Amended Site Certificate, May 2002
- Stateline Wind Project Wildlife Monitoring Annual Report, May 2003
- Final Order on Amendment #2, June 2003
Attachment A: Oregon Wildlife Monitoring Plan Attachment B: Revegetation Plan Attachment C: Resource Impact Avoidance and Mitigation Plan
- Second Amended Site Certificate, June 2003
- Stateline Wind Project Wildlife Monitoring Report: July 2001-December 2003, December 2004
- Final Order on Amendment #3, June 2005 [1.2 mb pdf]
Attachment A: Oregon Wildlife Monitoring Plan [121 kb pdf]
- Third Amended Site Certificate, June 2005 [172 kb pdf]
- Oregon Wildlife Monitoring Plan, January 2006 [118 kb pdf]
- Stateline Wind Project Wildlife Monitoring Report for 2006, September 2007 [2.9 MB pdf]
- Final Order on Amendment #4, March 2009 [976 kb pdf]
Attachment A (Wildlife Monitoring and Mitigation Plan) [138 kb pdf] Attachment B (Revegetation Plan) [78 kb pdf] Attachment C (Stateline 3 Habitat Mitigation Plan) [50 kb pdf]
- Fourth Amended Site Certificate, March 2009 [190 kb pdf]
|
|
|
|