| State Energy Program Projects |
|
|
|
 |
| Baker County |
|
| City |
County |
Project Owner |
Project Description |
Estimated Project Cost |
Amount Awarded |
| Baker City |
Baker |
Baker County Courthouse |
Add automated logic control system for HVAC system in courthouse |
$100,000 |
$65,000 |
|
|
 |
| Clatsop County |
|
| City |
County |
Project Owner |
Project Description |
Estimated Project Cost |
Amount Awarded |
| Seaside |
Clatsop |
Jewell School District |
Jewell School - Gym lighting project - Replace 8 lamp sportlights with 6 lamp T5 fixtures |
$15,000 |
$5300 |
|
|
 |
| Coos County |
|
| City |
County |
Project Owner |
Project Description |
Estimated Project Cost |
Amount Awarded |
| North Bend |
Coos |
North Bend School District |
North Bend Middle School - Domestic Hot Water system - Installation of high efficiency water heating units in place of current steam heat exchanger system.
|
$30,709 |
$20,472 |
| North Bend |
Coos |
North Bend School District |
Hillcrest Elementary - Domestic Hot Water system - Installation of high efficiency water heating units to replace sytem that is currently run off of one of the main oil burners.
|
$33,608 |
$20,472 |
| North Bend |
Coos |
North Bend School District |
North Bay Elementary - Lighting retrofit T-12 to T-8
|
$50,000 |
$35,000 |
|
|
 |
| Crook County |
|
| City |
County |
Project Owner |
Project Description |
Estimated Project Cost |
Amount Awarded |
| Prineville |
Crook |
Crook County High School |
Replace reheat coil, add additional venting, and upsize ductwork in art room to reach normal occupied temperature (69°F) |
$7,915 |
$7,123 |
| Prineville |
Crook |
Powell Butte Elementary School |
Replace 30 year old oil burner with new high efficiency oil burner |
$6,000 |
$5,600 |
|
|
 |
| Gillam County |
|
| City |
County |
Project Owner |
Project Description |
Estimated Project Cost |
Amount Awarded |
| Arlington |
Gilliam |
Arlington School District 3 |
Arlington High School - Lighting retrofit - Metal Halide to T-8 fixtures
|
$6,600 |
$6,600 |
| Arlington |
Gilliam |
Arlington School District 3 |
Arlington Elementary - Lighting retrofit. - Metal Halide to T-8 fixtures
|
$16,800 |
$16,800 |
| Condon |
Gilliam |
Condon School District 25J |
Condon High School - Gym Lighting - Replace 24 Metal halide fixtures with Hi-Efficiency Fluorescent Fixtures
|
$11,520 |
$8,640 |
|
|
 |
| Grant County |
|
| City |
County |
Project Owner |
Project Description |
Estimated Project Cost |
Amount Awarded |
| Long Creek |
Grant |
Long Creek School District #17 |
Long Creek School - Lighting retrofit throughout school including gym |
$49,899 |
$18,673 |
Canyon City
|
Grant |
Grant County Historical Museum |
Insulate, replace single pane windows, and replace 30 year old oil heating system with heat pumps |
$100,790 |
$97,790 |
Canyon City
|
Grant |
Canyon City Community Hall |
Add insulation and replace single pane windows |
$68,583 |
$68,583 |
|
|
 |
| Harney County |
|
| City |
County |
Project Owner |
Project Description |
Estimated
Project Cost
|
Amount Awarded |
| Crane |
Harney |
Crane Union High School |
Replace aluminum single pane windows in high school and dormitory with energy efficient windows.
|
$27,282 |
$16,625 |
| Burns |
Harney |
Lincoln Junior High |
Replace existing windows in Lincoln Junior High Building with new block frame insulated vinyl windows with sash replacement method.
|
$109,429 |
$76,601 |
| Burns |
Harney |
Burns High School |
Replace 276 windows in high school building |
$272,081 |
$190,457 |
| Burns |
Harney |
Harney County Library |
Replace 10,200 sq. ft. of windows and glass doors, add insulation |
$75,000 |
$70,000 |
| Hines |
Harney |
Oregon Department of Fish & Wildlife |
Upgrade windows, insulation, lighting and HVAC in Hines District Office |
$30,000 |
$20,000 |
|
|
 |
| Hood River County |
|
| City |
County |
Project Owner |
Project Description |
Estimated Project Cost |
Amount Awarded |
| Hood River |
Hood River |
Hood River County School District |
Cascade Locks School - Installation of DDC system, comprehensive lighting retrofit and retrocommissioning of all HVAC equipment
|
$79,628 |
$31,301 |
| Hood River |
Hood River |
Hood River County School District |
May Street Elementary - Control system upgrade, comprehensive lighting retrofit, and retrocommissioning of HVAC equip.
|
$195,472 |
$39,225 |
| Hood River |
Hood River |
Hood River County School District |
Frankton School - Control system upgrade, comprehensive lighting retrofit, steamtrap replacement and retrocommissioning of HVAC equip.
|
$188,495 |
$49,964 |
|
|
 |
| Jefferson County |
|
| City |
County |
Project Owner |
Project Description |
Estimated Project Cost |
Amount Awarded |
| Madras |
Jefferson |
Jefferson County Courthouse |
Replace older magnetic ballasts and T-12 lamps containing PCBs with energy efficient ballasts and environmentally friendly, energy efficient T-8 lamps |
$25,600 |
$25,600 |
|
|
 |
| Klamath County |
|
| City |
County |
Project Owner |
Project Description |
Estimated Project Cost |
Amount Awarded |
| Klamath Falls |
Klamath |
Oregon Institute of Technology |
Lighting, controls, Demand Cotrol Ventilation, insulation, HVAC, and other conservation and energy efficiency measures in multiple buildings on OIT campus |
$548,803 |
$82.625 |
|
|
 |
| Lane County |
|
| City |
County |
Project Owner |
Project Description |
Estimated Project Cost |
Amount Awarded |
| Eugene |
Lane |
Bethel School District |
Fairfield Elementary - Lighting retrofit, T-12 change out
|
$24,000 |
$22,400 |
| Eugene |
Lane |
Bethel School District |
Malabon Elementary - Lighting retrofit, T-12 change out
|
$50,000 |
$45,000 |
| Springfield |
Lane |
Springfield Public Schools |
Admin. Bldg - Lighting retrofit - T-12 to T-8
|
$10,000 |
$5,000 |
| Springfield |
Lane |
Springfield Public Schools |
Elizabeth Page Elementary School - Building Envelope Retrofit -Add Insulation to building envelope.
|
$20,000 |
$15,000 |
| Springfield |
Lane |
Springfield Public Schools |
Installation of occupancy sensors in multiple schools throughout the SD |
$112,131 |
$43,000 |
|
|
 |
| Malheur County |
|
| City |
County |
Project Owner |
Project Description |
Estimated Project Cost |
Amount Awarded |
| Adrian |
Malheur |
Adrian High School |
Upgrade existing lighting in high school to include classrooms, hallways, restrooms, and shop building
|
$26,080 |
$11,885 |
| Jordan Valley |
Malheur |
Jordan Valley High School |
Replacement of 15 windows on east side of Jordan Valley High School
|
$20,950 |
$13,950 |
| Ontario |
Malheur |
City of Ontario |
Upgrade existing lighting in older buildings at Ontario Water Treatment Plant with environmentally friendly, energy efficient lighting
|
$35,000 |
$17,500 |
|
|
 |
| Morrow County |
|
| City |
County |
Project Owner |
Project Description |
Estimated
Project Cost
|
Amount Awarded |
| Ione |
Morrow |
Ione High School |
Shop building weatherization and HVAC |
$91,955 |
$38,153 |
|
|
 |
| Umatilla County |
|
| City |
County |
Project Owner |
Project Description |
Estimated Project Cost |
Amount Awarded |
| Stanfield |
Umatilla |
Stanfield School District |
Stanfield School District Office - HVAC Upgrade
|
$117,764 |
$29,796 |
| Stanfield |
Umatilla |
Stanfield School District |
Stanfield School District Office - Lighting retrofit at several schools in SD
|
$166,137 |
$37,544 |
| Milton-Freewater |
Umatilla |
City of Milton-Freewater |
Replace windows and upgrade lighting. Replace baseboard heating with air source heat pumps and add supporting ductwork at City Hall
|
$175,000 |
$134,000 |
| Milton-Freewater |
Umatilla |
City of Milton-Freewater |
Replace existing T-12 lamps and incandescent lighting with T-8 lamps. Replace 13 windows with Energy Star windows at Saager Fire Station |
$9,000 |
$7,200 |
| Milton-Freewater |
Umatilla |
City of Milton-Freewater |
Replace existing T-12 lamps and incandescent lighting with T-8 lamps at City Shop and Out Buildings
|
$28,000 |
$16,000 |
| Milton-Freewater |
Umatilla |
City of Milton-Freewater |
Replace existing T-12 lamps and incandescent lighting with T-8 lamps at South Fire Station
|
$3,530 |
$1,700 |
| Pendleton |
Umatilla |
Umatilla County |
Umatilla County Juvenile Center
-
Upgrade existing, antiquated controls and adjust airflow to better serve the space
-
Replace electric resistance heating with ground-coupled water source heat pumps
-
Insulate exterior walls
-
Replace T-12 lamps with T-8 lamps
|
$570,400 |
$185,000 |
|
|
 |
| Wasco County |
|
| City |
County |
Project Owner |
Project Description |
Estimated Project Cost |
Amount Awarded |
| Maupin |
Wasco |
Oregon Department of Fish & Wildlife |
Small hydro system to generate the vast majority of the electricity needs at the Oak Springs Hatchery
|
$300,000 |
$200,000 |
|
|
 |
| Washington County |
|
| City |
County |
Project Owner |
Project Description |
Estimated Project Cost |
Amount Awarded |
| Beaverton |
Washington |
Beaverton School District |
Special Ed. Admin. Bldg - Replace the four existing furnaces and split system air conditioning units with high efficiency heat pumps. |
$37,200 |
$37,200 |
|
|
 |
| Wheeler County |
|
| City |
County |
Project Owner |
Project Description |
Estimated Project Cost |
Amount Awarded |
| Fossil |
Wheeler |
Fossil School District |
Fossil High School - Gym Lighting - Replace 32 Metal halide fixtures with Hi-Efficiency Fluorescent Fixtures
|
$19,200 |
$15,360 |
| Mitchell |
Wheeler |
Mitchell School District |
Mitchell School - Lighting retrofit in school, including the gym. |
$26,260 |
$11,670 |
|
|
| |
|
|