Oregon Seal
Text-Only Site State Directory Agencies A-Z Accessibility
  Advanced
Help
www.oregon.gov

Wetlands/Waterways Removal-Fill

waterway


Menu
About Us

Contact Us

Administrative Rules

Statutes

Forms|Publications

Application Help

Check Application Status

Permit Application Fees

Permit Information

General Authorizations

Wetland Resources

Mitigation

Mitigation Banks

Essential Salmon Habitat

Scenic Waterways

InWater Work Periods

Land Board Awards

 
Minor Impacts to Freshwater Wetlands
wetland development
Wetland development. Photo by Janet Morlan
General Authorization for Minor Impacts to Freshwater Wetlands in Urban-type Areas
 
To be eligible for the General Authorization for minor impacts to freshwater wetlands located within urban growth boundaries or urban unincorporated communities, a project must meet the following eligibility requirements:
  • The removal or fill is located in a freshwater wetland and involves less than 0.1 (one-tenth) acre permanent impacts to wetlands.
  • The area does not contain state or federal listed species.
  • The wetland is not designated in the local comprehensive use plan as a locally significant wetland.
  • The location is beyond the floodway or flood fringe area as designated on maps approved by the Federal Emergency Management Agency.
  • The activity is not located adjacent to an estuary.
  • The wetlands is not within an area designated as essential salmon habitat.
The following projects are NOT eligible for this authorization:
  • Projects that include any structure, use or activity subject to another General Authorization, unless it is incidental to the project or is necessary to provide fish passage or for the structural integrity of the project.
Other mandatory requirements:
  • If the project is within a State Scenic Waterway, you will also be required to obtain a State Scenic Waterway permit. We will automatically process the State Scenic Waterway permit that will be incorporated into the letter of authorization.
  • An approved wetland delineation is required for a complete application.
  • A compensatory wetland mitigation plan must be submitted with the application.
To apply for this authorization, you must:
 
NOTE: The addendum MUST accompany your application.
 
 
 
 
For a more detailed description of additional eligibility and mandatory requirements, consult OAR 141-089-0585-615. (At Secretary of State site, press CTRL-F, key in 0585, and press Enter)
 
If you have further questions about a specific project, contact the DSL Resource Coordinator for your county.
 
 
 
 
 
Back to the Top